Project Milestones¶
| Milestone | Suggested timing | Evidence |
|---|---|---|
| Topic + initial bibliography | Week 3 | 5–10 sources, one-sentence RQ |
| Proposal | Week 5 | scoped method + baseline + subjects |
| Reproduction baseline | Week 7 | baseline runs end-to-end |
| Prototype / extension | Week 9 | method implementation |
| Pilot evaluation | Week 10 | small result + failure analysis |
| Full experiment | Week 12 | frozen subjects/configs |
| Artifact freeze | Week 13 | reproducibility check |
| Presentation + report | Week 14 | final evidence |
Tip
Freeze the experiment design before looking repeatedly at the final test results. Otherwise tuning can silently turn the test set into a validation set.